Projects

Scope implemented by Polimex Energetyka:
- assembly of steel structures (4,200 tons)
- assembly of technological devices (250 tons)
- assembly of light casings (10,500 m2)
- assembly of technological pipelines (800 tons)
Scope implemented by Polimex Energetyka:
- assembly of steel structures (400 tons)
- integration and assembly of ducts (400 tons)
- dismantling of ducts (150 tons)
- assembly of technological devices (52 tons)
- assembly of technological pipelines (55 tons)
Scope implemented by Polimex Energetyka:
- assembly of steel structures (450 tons)
- assembly of technological devices (520 tons)
- assembly of light casings (800 m2)
- assembly of technological pipelines (220 tons)
- Scope of works: engineering, workshop documentation,fabrication, delivery and erection of a steel structure including strengthening of existing elements, civil works and also delivery and erection of cable ladder elements together with wall and roof cold cladding as a support for new electrical cables to be installed during repair maintenance of the object.
- Tonnage of project: about 180 tons
- Location: iJmuiden, Netherlands
- Date of realization: 2020 / 2021
-
PROJECT KEMSLEY, ENGLAND (UK)
Scope of works: delivery, prefabrication and erection of pipelines and installation of equipment.
Tonnage of project: 69,7 tons of piping, 7 tons of support structure, 14,1 tons of equipment.
Location: Kemsley, England
- PROJECT EARLS GATE IN SCOTLAND (UK)
Assembly of a flue gas treatment unit and the support structure (200 tons) along with the installation of equipment: flue gas ducts, a bag filter, silos, fans and conveyors (254 tons). Project implemented in 2020.
- PROJECT RAMBERVILLERS (FRANCJA)
Assembly of a support structure for the boiler (428 tons) and a flue gas treatment unit (182 tons). Installation of equipment (284 tons): ducts, a bag filter, an SCR reactor, fans, silos or mechanical conveyors. Project implemented in 2020.
- Workshop project, delivery and assembly of steel structures (805 tons) for the boiler room in the Palm paper mill, Aalen-Neukochen, Germany.
- Workshop project, delivery and assembly of steel structures along with a casing for the wall and the roofs of a technological installation (1,100 tons) for the transportation of metallurgical materials to Amsterdam, the Netherlands
- Workshop project, delivery and assembly of steel structures for the boiler room in Annecy, France (130 tons)
Delivery of steel structures for the boiler in Hooton, UK (470 tons)
EPC
Supply and installation of two turbine generator sets with a capacity of 100 MWe each, along with design and accompanying work in the Żerań CHP. Client: the Power Plants in Warsaw SA (PGNiG Termika SA). Contract value: PLN 140 million Tz11 + PLN 171 million Tz12.
Implementation of Wet Flue Gas Desulphurization Installation in the Power Plant Rybnik. Client: Power Rybnik. Value of the contract: PLN 228 million.
Construction of the installation of renewable energy production based on biomass in the CHP Bialystok SA. Client: CHP Bialystok SA. Contract value: PLN 85 million.
Construction of a new Water Treatment Plant in the Nitrogen Plant in Kędzierzyn. Contract value: PLN 63 million.
Coaling plant construction in Belchatow. Client: SANDVIK Mining and Construction. Contract value: PLN 83.8 million.
Design, construction, supply of machinery and equipment, and installation of a complete Flue Gas Desulphurization block No. 10 - 500 MW. Client: "Kozienice" SA Power Plant (ENEA Production SA). Contract value: PLN 75.5 million.
Construction of a new power unit with a fluidized bed boiler, backpressure turbine, two peak boilers and heat accumulator in the Bielsko-Biala EC1 Power Plant. Client: PKE SA. Contract value: PLN 409.7 million.
Construction of a catalytic denitrification plant for OP-430 block boilers No. 10, 14, 15 and OP-380 boiler No. 11 in Siekierki. Client: Vattenafall Heat Poland SA (PGNiG Termika SA). Contract value: PLN 140 million.
Professional assembly
PLN Pressure part assembly in two boilers with a capacity of 1100 MW at Neurath. Client: Hitachi Power Europe, Alstom Power Boiler. Contract value: PLN 107.1 million.
Pressure part assembly in a boiler within the package No. 1,2,4,5 for a block of 858 MW in the Belchatow power plant. Client: ALSTOM Power Sp. z o. o. and RAFAKO SA. Boiler Factory. Contract value: PLN 59.5 million.
Foreign contracts
PLN PAPER MILL IGGESUND, SWEDEN. Scope of works: supply and installation of steel structures with walls and roof construction. Client: Andritz Oy. Net value of the contract: PLN 31 million.
WASTE TO ENERGY PLANT, HELSINGBORG, SWEDEN. Scope of works: supply and erection of steel structure and channels (c. 1800 tons), installation of a boiler (about 800 tons), delivery and installation of piping (about 150 tons), installation of process equipment. Client: Babcock & Wilcox Vølund A/S, NCC Construction Sverige AB. Value: PLN 38.8 million.
IGNIS POWER PLANT, SPREMBERG, GERMANY. Scope of works: supply and installation of steel structures. Client: Baumgarte Boiler Systems GmbH. Value: PLN 15.2 million.
PULP MILL ENCE, HUELVA, SPAIN. Scope of works: supply and installation of steel structures with walls and roof construction. Client: Andritz Oy. Value: PLN 13.9 million