Polimex-Mostostal made the best offer in the tender for the boiler in Kozienice
Enea Wytwarzanie selected Polimex-Mostostal's bid for the modernization of the boiler unit No. 10 in Kozienice. Value of the offer amounts to PLN 15.7 million.
When choosing the best bid, price was taken into account (90 percent) and warranty (10 percent). The Employer provides that the task will be carried out in the period from March to July 2014. Polimex-Mostostal is already executing in Kozienice a new block with a capacity of 1075 MW. The scope includes construction and assembly work, which amounts to about PLN 6.3 billion gross. Polimex-Mostostal also executes construction and assembly works under a contract for the construction of flue gas desulphurisation plant. The value of the order reaches PLN 78.6 million gross.